Construction of the Complete Transformer Substation (CTS)
The project includes the comprehensive setup of a transformer substation based on two powerful Siemens transformers, each with a capacity of 2500 kVA.
The work involves the construction of the substation, the dismantling of existing transformers, and the installation of new equipment, such as transformers, bus bridges, and high-voltage switchgear.
We are currently actively working on the connections and performing commissioning activities.
Upon completion of the project, the production capacity of the glass products workshop will be increased, which will positively impact the Customer's capabilities and their competitiveness in the market.
We thank all the members of the ELAKS team for their hard work and dedication in implementing this project.
Together we will reach new heights and make our company even stronger!