FULL PRODUCTION CYCLE
We provide a full range of services to help you automate your manufacturing processes. We design, implement, and support industrial automation solutions based on equipment manufactured by world’s leading producers
Our solutions
Object
Name of workWork
Year
"Vinnytsia Poultry Farm" LLC, Vinnytsia, UkraineCompound feed production line. ACS TP introduction of liquid components (preservatives) into compound feed. Design, application software, manufacture and supply of equipment, installation, commissioning works
«Starokonstantinovsky OEZ» LLC, UkraineConnecting a 29 MW steam turbine generator to a 10.5 kV TPP main switchgear. ACS TP of the fuel supply unit and areas of auxiliary equipment of the thermal power plant of the oil extraction plant with a capacity of 3000 t/day. Design, supply of equipment, electrical installation, installation and commissioning works
«Kharkiv heat networks» KP, UkraineCentral heating points, pumping stations, boiler houses. ASU TP. Construction of the SCADA system. commissioning works.
«Mondelis Ukraine» PrAT, Trostyanets, UkraineCookie production line. ASU TP. Production and supply of equipment, installation, commissioning works
«Mondelis Ukraine» PrAT, Trostyanets, UkraineStorage of glucose-fructose syrup. ASU TP. Design, application software, manufacture and supply of equipment, installation, commissioning works
Drywall workshop, unloading line, sawing. ASU TP. Design and application software/TIA Portal production and supply of electrical equipment and materials, electrical installation, commissioning
«Nizhyn fat processing plant» PrAT, UkraineOil-press and gun-fan shop. ASU TP. Production and supply of equipment, installation, commissioning works
Mondelēz International, ItalyFactory acceptance test (FAT) of hardware and software components of the automatic line of secondary packaging of cookies in production in Italy
Okatka production workshop. Reconstruction of engineering networks in the construction zone of the complex. Pulp pump station for emptying the emergency capacity of the Central Military District (NS-CVO). Production and supply of equipment and materials
Mining and beneficiation plant. KazakhstanDOF. ACS TP of the conveyor sampling and preparation system. Design, application software